Most homeowners in Budleigh Salterton and the surrounding villages ask us the same question before anything else: how long will we be living on a building site? The honest answer is that the on-site work is usually the shorter part of the job. Getting to the first spade in the ground often takes longer than the build itself, so it helps to understand both halves.
For the construction phase alone, assuming drawings are approved and the site is clear, these are the ranges we work to in practice. Weather, ground conditions and the level of finish you choose can move things either way, so treat them as a guide rather than a promise.
A build is not finished when the roof goes on. Second fix, plastering, decorating and floor finishes typically account for the final third of the programme, and it is this last stretch that most people underestimate.
Before any work starts you need drawings, and in many cases planning consent. East Devon District Council aims to decide householder applications within 8 weeks, but validation, neighbour consultation and any requests for amendments can stretch this to 10 to 14 weeks. Much of Budleigh Salterton sits within a conservation area and close to the coast, so materials and roof forms attract closer scrutiny than they might elsewhere.
Some single storey extensions fall under permitted development, which avoids a full application. You will still want a lawful development certificate for peace of mind and for when you sell, and that takes a further 6 to 8 weeks. Building regulations drawings, structural calculations and a party wall notice to neighbours, where one applies, run alongside this and need to be sorted before the builder can price the job properly.
Realistically, allow 4 to 6 months from first conversation with a designer to being ready to start on site. Starting the paperwork in the autumn is a sensible way to be building by spring.
Ground conditions are the biggest unknown locally. Parts of East Devon sit on clay, and tree roots or drains near the footings can mean deeper excavations than the drawings assumed. A building control inspector will look at the trench before concrete goes in, and if they ask for more depth that is a day or two lost plus extra muck away.
Steel beams and bespoke glazing are the other common culprits. Structural steel usually has a 2 to 3 week lead time once the fabricator has final dimensions, and large sliding or bifold doors can be 6 to 10 weeks from order. A good builder will order these well before they are needed, but any late change to the opening size starts the clock again.
The single most useful thing you can do is make your decisions early. Have the kitchen designed, the flooring chosen and the door supplier confirmed before the footings are dug. Every choice made in advance is one less pause waiting for a delivery or a price.
Ask your builder for a written programme with the main stages dated, and agree how changes will be handled. A weekly ten minute walk round the site with whoever is running the job catches small issues before they become a week's delay. Finally, be realistic about living arrangements. A rear extension that opens into the kitchen usually means a few weeks without a working kitchen, and planning for that up front makes the whole process far less stressful.
Yes, and many are. Groundworks and brickwork are more exposed to wet weather, so allow an extra week or two in the programme between November and February, but once the roof is on and the building is watertight the season makes little difference.
For most single storey rear extensions, no. The builder can keep the existing house sealed off until the knock through, which is usually left until the new structure is watertight. Double storey work or a full kitchen refit may make a short stay elsewhere more comfortable but it is rarely essential.
Reputable local builders are often booked 3 to 6 months ahead, so speak to them while your drawings are still with the planners rather than after consent arrives. That way the start date lines up with your approval and you are not waiting for a slot.